September 8 (Tuesday night/Wednesday morning)
September 9 (Wednesday night/Thursday morning)
Nightly, midnight to 5:00 a.m.
Activity: Ramp construction
September 1
Overnight (Tuesday night/Wednesday morning), 1:00 a.m. to 5:00 a.m.
Activity: Ramp construction
August 31
Overnight (Monday night/Tuesday morning), midnight to 5:00 a.m.
Activity: Ramp construction
August 31
Overnight (Monday night/Tuesday morning), 1:00 a.m. to 5:00 a.m.
Activity: Ramp construction
August 25-27
Nightly, 11:00 pm to 5:00 a.m.
Activity: Bridge demolition
August 24
Overnight, 11:00 p.m. to 5:00 a.m.
Activity: Bridge demolition
August 23
Overnight, 10:00 p.m. to 5:30 a.m.
Activity: Bridge demolition
August 25
Nightly, 11:00 p.m. to 5:00 a.m.
Activity: Ramp construction
August 18-19
Nightly, midnight to 5:00 a.m.
Activity: Road construction
August 17-18
Nightly, midnight to 4:00 a.m.
Activity: Ramp construction